Final Engineering Design and Construction of watermain underground at King Street (Webster to George), in conjunction with road reconstruction works at the same location

Wilmot, Ontario

completeDrinking WaterCWWF
Federal contribution
$30,919
Federal share39%

of $80.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 26, 2017
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Wilmot
Construction start
Apr 1, 2017(actual)
Construction end
Nov 30, 2017(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Dec 31, 2017

Also in Wilmot

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49666 in the federal list. How to read these figures.