Final Engineering Design and Construction of watermain underground at King Street (Webster to George), in conjunction with road reconstruction works at the same location
Federal contribution
$30,919
Federal share39%
of $80.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 26, 2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Wilmot
- Construction start
- Apr 1, 2017(actual)
- Construction end
- Nov 30, 2017(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Dec 31, 2017
Also in Wilmot
- Replacement of Structure 34/B-T9 over the Nith River$1.8M
- Foxboro Wastewater Treatment Plant Upgrades$1.5M
- Snyder's Road West Watermain Replacement$844.8K
- Preliminary Design, Engineering and Construction of Storm Sewer on the Wilmot Employment Lands site, located on the North Side of the Highway 7/8 corridor between Kitchener and Stratford$425.5K
- Rehabilitation of Shade Street Bridge$242.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49666 in the federal list. How to read these figures.