Back to projects

Safety and outside signalling

Laval, Quebec

completePublic TransitPTIF
Federal contribution
$121,733
Federal share50%

of $243.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2017
201820192020
Built

Approved 2 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jan 1, 2018(actual)
Construction end
Jan 28, 2020(actual)

Also in Laval