Back to projects

Implementation of a centralized information and client relations system

Laval, Quebec

completePublic TransitPTIF
Federal contribution
$330,008
Federal share50%

of $660.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 2, 2018
2018201920202021
Built

Approved 6 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Dec 20, 2017(actual)
Construction end
Mar 31, 2021(actual)

Also in Laval