Back to projects

Cove Bay Water Treatment Plant

Bowen Island, British Columbia

completeDrinking WaterSCF
Federal contribution
$1.9M
$1,945,183
Federal share33%

of $5.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 11, 2017
2018201920202021
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Mar 20, 2020(actual)
Construction end
Jul 30, 2021(actual)

Against the original forecast

  • Construction start3 months lateforecast Jan 2, 2020
  • Construction end3 months lateforecast Apr 30, 2021

Also in Bowen Island

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49712 in the federal list. How to read these figures.