Schedule

Announced and approvedAug 5, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jan 17, 2022(actual)
Construction end
Oct 31, 2023(actual)

Against the original forecast

  • Construction start9 months lateforecast Apr 21, 2021
  • Construction end2 months earlyforecast Dec 31, 2023