Bowen Island - Multi-Use Path: Section N1
Bowen Island, British Columbia
Federal contribution
$517,600
Federal share80%
of $647.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 5, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Municipality of Bowen Island
- Construction start
- Jan 17, 2022(actual)
- Construction end
- Oct 31, 2023(actual)
Against the original forecast
- Construction start9 months lateforecast Apr 21, 2021
- Construction end2 months earlyforecast Dec 31, 2023
Also in Bowen Island