Bowen Island - Eagle Cliff and Cove Bay Water Systems Connection and Improvement

Bowen Island, British Columbia

underwayDrinking WaterGIS
Federal contribution
$841,200
Federal share40%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 3, 2023
202420252026
BuiltForecast

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Sep 15, 2025(actual)
Construction end
Jun 30, 2026(forecast)

Against the original forecast

  • Construction start4 months lateforecast May 15, 2025