City of Grand Forks 2017 Sewer Phasing Plan
Federal contribution
$50,000
Federal share50%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Grand Forks
- Construction start
- Feb 2, 2017(actual)
- Construction end
- Mar 30, 2018(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jan 16, 2017
- Construction end4 months lateforecast Nov 30, 2017
Also in Grand Forks
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49860 in the federal list. How to read these figures.