Lift Station Upgrade with SCADA

Smoky River No. 130, Alberta

completeWastewaterCWWF
Federal contribution
$78,000
Federal share50%

of $156.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2017
201820192020
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 30, 2018(actual)
Construction end
Feb 20, 2020(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2018
  • Construction end6 weeks earlyforecast Mar 31, 2020