Lift Station Upgrade with SCADA
Federal contribution
$78,000
Federal share50%
of $156.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
201820192020
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipal District of Smoky River
- Construction start
- Jul 30, 2018(actual)
- Construction end
- Feb 20, 2020(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2018
- Construction end6 weeks earlyforecast Mar 31, 2020
Also in Smoky River No. 130
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49909 in the federal list. How to read these figures.