Lift Station Upgrade with SCADA
Federal contribution
$78,000
Federal share50%
of $156.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
201820192020
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipal District of Smoky River
- Construction start
- Jul 30, 2018(actual)
- Construction end
- Feb 28, 2020(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2018
- Construction end8 weeks lateforecast Dec 31, 2019
Also in Smoky River No. 130