Lift Station Upgrade with SCADA

Smoky River No. 130, Alberta

completeWastewaterCWWF
Federal contribution
$78,000
Federal share50%

of $156.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2017
201820192020
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 30, 2018(actual)
Construction end
Feb 28, 2020(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2018
  • Construction end8 weeks lateforecast Dec 31, 2019

Also in Smoky River No. 130

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49910 in the federal list. How to read these figures.