Back to projects

Treated Storage and Distribution Upgrades

Warner, Alberta

completeDrinking WaterCWWF
Federal contribution
$154,824
Federal share42%

of $366.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2017
20182019
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Warner No. 5 County
Construction start
Jul 18, 2018(actual)
Construction end
Mar 14, 2019(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 1, 2018
  • Construction end2 weeks earlyforecast Mar 31, 2019

Also in Warner

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49955 in the federal list. How to read these figures.