Treated Water Distribution Upgrades
Federal contribution
$118,101
Federal share37%
of $315.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
20182019
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Warner No. 5 County
- Construction start
- Jul 18, 2018(actual)
- Construction end
- Mar 14, 2019(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 1, 2018
- Construction end2 weeks earlyforecast Mar 31, 2019
Also in Warner
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49956 in the federal list. How to read these figures.