Treated Water Distribution Upgrades

Warner, Alberta

completeDrinking WaterCWWF
Federal contribution
$118,101
Federal share37%

of $315.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2017
20182019
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Warner No. 5 County
Construction start
Jul 18, 2018(actual)
Construction end
Mar 14, 2019(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 1, 2018
  • Construction end2 weeks earlyforecast Mar 31, 2019