Back to projects

North Pump Station Upgrade Phase 2

Taber, Alberta

completeDrinking WaterCWWF
Federal contribution
$175,000
Federal share50%

of $350.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2017
201820192020
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Taber
Construction start
Sep 30, 2019(actual)
Construction end
Apr 21, 2020(actual)

Against the original forecast

  • Construction start15 months lateforecast Jun 30, 2018
  • Construction end4 months lateforecast Dec 31, 2019