North Pump Station Upgrade Phase 2
Federal contribution
$175,000
Federal share50%
of $350.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
201820192020
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Taber
- Construction start
- Sep 30, 2019(actual)
- Construction end
- Apr 21, 2020(actual)
Against the original forecast
- Construction start15 months lateforecast Jun 30, 2018
- Construction end4 months lateforecast Dec 31, 2019
Also in Taber