Purchase of replacement specialized transit bus

Leduc, Alberta

completePublic TransitPTIF
Federal contribution
$42,881
Federal share46%

of $92.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 5, 2017
2018
Built

Approved 5 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Leduc
Construction start
Feb 27, 2017(actual)
Construction end
Mar 8, 2018(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jan 1, 2017
  • Construction end3 weeks earlyforecast Mar 31, 2018

Also in Leduc

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49963 in the federal list. How to read these figures.