Construct concrete bus stops for passengers to safely await buses

Leduc, Alberta

completePublic TransitPTIF
Federal contribution
$25,500
Federal share50%

of $51.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 5, 2017
20182019
Built

Approved 5 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Leduc
Construction start
Oct 1, 2017(actual)
Construction end
Jun 28, 2019(actual)

Against the original forecast

  • Construction start9 months lateforecast Jan 1, 2017
  • Construction end2 months earlyforecast Sep 1, 2019

Also in Leduc

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49964 in the federal list. How to read these figures.