Pinecrest Garage, localized bus bay concrete repairs, sidewalks and asphalt replacement

Ottawa, Ontario

completePublic TransitPTIF
Federal contribution
$735,201
Federal share49%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 17, 2017
2018
Built

Approved 8 months before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Ottawa
Construction start
Mar 1, 2017(actual)
Construction end
May 31, 2018(actual)

Against the original forecast

  • Construction start11 months lateforecast Apr 1, 2016
  • Construction end3 months lateforecast Mar 14, 2018

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49979 in the federal list. How to read these figures.