Rehabilitation of Well # 3 located on 6th Street including New Casing and pump
Federal contribution
$9,237
Federal share46%
of $20.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 24, 2017
ApprovedMar 27, 2018
2018
Built
Approved 10 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Armstrong
- Construction start
- Oct 10, 2017(actual)
- Construction end
- Oct 30, 2017(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 1, 2017
Also in Armstrong