Canada's Diversity Gardens
Federal contribution
$35.0M
$35,000,000
Federal share28%
of $126.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 29, 2017
201820192020202120222023
Built
Approved 5 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Assiniboine Park Conservancy
- Construction start
- May 29, 2017(actual)
- Construction end
- Dec 19, 2022(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Jul 3, 2017
- Construction end7 weeks lateforecast Oct 28, 2022
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50109 in the federal list. How to read these figures.