Rehabilitate the Victorian Village Stormwater Management Pond at 467 Victoria Street

Scugog, Ontario

completeWastewaterCWWF
Federal contribution
$59,816
Federal share50%

of $119.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 28, 2017
201820192020
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jun 1, 2018(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start12 months lateforecast Jun 1, 2017
  • Construction end4 months lateforecast Nov 30, 2019