Rehabilitate the Victorian Village Stormwater Management Pond at 467 Victoria Street
Federal contribution
$59,816
Federal share50%
of $119.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 28, 2017
201820192020
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the Township of Scugog
- Construction start
- Jun 1, 2018(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start12 months lateforecast Jun 1, 2017
- Construction end4 months lateforecast Nov 30, 2019
Also in Scugog
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50216 in the federal list. How to read these figures.