Installation of Water Meters on existing water services in Hamlet of Newington

South Stormont, Ontario

completeDrinking WaterCWWF
Federal contribution
$37,500
Federal share50%

of $75.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of South Stormont
Construction start
Mar 15, 2018(actual)
Construction end
Feb 14, 2020(actual)

Against the original forecast

  • Construction start14 months lateforecast Jan 15, 2017
  • Construction end3 months lateforecast Oct 31, 2019

Also in South Stormont