Installation of Water Meters on existing water services in Hamlet of Newington
Federal contribution
$37,500
Federal share50%
of $75.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of South Stormont
- Construction start
- Mar 15, 2018(actual)
- Construction end
- Feb 14, 2020(actual)
Against the original forecast
- Construction start14 months lateforecast Jan 15, 2017
- Construction end3 months lateforecast Oct 31, 2019
Also in South Stormont