Lateral inspections to determine the condition of the lateral collection system feed lines from customers.
Federal contribution
$10,000
Federal share50%
of $20.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 17, 2017
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of McGarry
- Construction start
- Sep 21, 2017(actual)
- Construction end
- Oct 16, 2017(actual)
Against the original forecast
- Construction start8 months lateforecast Feb 1, 2017
- Construction end5 months earlyforecast Mar 31, 2018
Also in McGarry
- Virginiatown Collection and Distribution Upgrades$925.3K
- Repairs and Upgrade to Public Works Garage$80.0K
- Repair of 10 water valves in the drinking water distribution system$20.1K
- Design needed for the separation of the drinking water and the sewer line as the water line is crossing the sewer line. (phase 1 of 2)$5.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50253 in the federal list. How to read these figures.