Cochenour Wastewater Lift Station, Highway 125, Pump Rebuilds

Red Lake, Ontario

completeWastewaterCWWF
Federal contribution
$3,301
Federal share50%

of $6.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 17, 2017
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Red Lake
Construction start
Oct 10, 2017(actual)
Construction end
Nov 29, 2017(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 1, 2017
  • Construction end5 weeks earlyforecast Dec 31, 2017

Also in Red Lake

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50285 in the federal list. How to read these figures.