Bow Falls Trail Upgrade

Banff, Alberta

completeActive TransportationNRT
Federal contribution
$57,675
Federal share38%

of $151.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 30, 2009
2010
Built

Approved 2 months before the announcement.

Program
National Recreational Trails Program
Ultimate recipient
Town of Banff
Construction start
May 26, 2009(actual)
Construction end
Mar 31, 2010(actual)