Banff Centre Ventilation Upgrades Bundle
Federal contribution
$2.9M
$2,880,000
Federal share80%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 19, 2024
20242025
Built
Approved 10 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Banff Centre for Continuing Education
- Construction start
- Jan 3, 2024(actual)
- Construction end
- Apr 7, 2025(actual)
Against the original forecast
- Construction start6 months earlyforecast Jul 1, 2024
- Construction end3 months lateforecast Dec 31, 2024