Banff Centre Ventilation Upgrades Bundle

Banff, Alberta

completeVentilationCVRIS
Federal contribution
$2.9M
$2,880,000
Federal share80%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 19, 2024
20242025
Built

Approved 10 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jan 3, 2024(actual)
Construction end
Apr 7, 2025(actual)

Against the original forecast

  • Construction start6 months earlyforecast Jul 1, 2024
  • Construction end3 months lateforecast Dec 31, 2024

Also in Banff

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67639 in the federal list. How to read these figures.