Banff Pedestrian/Cyclist Bridge to Enhance Transit Connectivity

Banff, Alberta

completeActive TransportationPTIS
Federal contribution
$2.2M
$2,157,627
Federal share40%

of $5.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 4, 2021
20222023
Built

Approved 6 weeks before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
Nov 1, 2021(actual)
Construction end
Mar 31, 2023(actual)

Against the original forecast

  • Construction end9 months lateforecast Jun 30, 2022