Back to projects

Banff Transit Priority and Connectivity Infrastructure

Banff, Alberta

completeActive TransportationPTIS
Federal contribution
$750,000
Federal share40%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 19, 2024
2024
Built

Approved 7 months before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
May 3, 2024(actual)
Construction end
Sep 16, 2024(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Apr 1, 2024
  • Construction end6 weeks earlyforecast Oct 31, 2024

Also in Banff

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67713 in the federal list. How to read these figures.