Squamish Trail Upgrade
Federal contribution
$119,801
Federal share50%
of $239.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 30, 2009
2010
Built
Approved 2 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- British Columbia Off-Road Motorcycle Association: BCORMA
- Construction start
- May 26, 2009(actual)
- Construction end
- Mar 31, 2010(actual)
Also in Squamish
- Brennan Park Recreation Centre Retrofit and Upgrade$11.8M
- Squamish - Brennan Park Recreation Centre Building Envelope Upgrade$5.7M
- Squamish - Mamquam Wastewater Treatment Plant Upgrade$4.0M
- Squamish - Xwu'nekw Park Sea Dike at Mamquam Blind Channel$2.2M
- Squamish River Dike Raising - Upper Jimmy Jimmy (Judd) Slough$2.2M