Pye Mountain ATV Trails
Campbell River, British Columbia
Federal contribution
$47,675
Federal share39%
of $122.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 13 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Campbell River ATV Club
- Construction start
- Jun 1, 2015(actual)
- Construction end
- Dec 21, 2015(actual)
Also in Campbell River
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50470 in the federal list. How to read these figures.