Trail Rehabilitation
Federal contribution
$11,690
Federal share50%
of $23.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 30, 2009
2010
Built
Approved 2 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Club d'Auto-Neige le Sapin d'Or Inc.
- Construction start
- May 26, 2009(actual)
- Construction end
- Mar 31, 2010(actual)
Also in Boischatel
- Upgrading to standards the drinking water treatment plant$4.6M
- Upgrade water mains and sewer lines under Royale Avenue$1.0M
- Development of sports and recreational facilities at Parc des Saphirs$586.7K
- Program for the renewal of drinking water and wastewater pipes$398.8K
- Water Systems Extension - rue des Saphirs$180.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50497 in the federal list. How to read these figures.