Development of sports and recreational facilities at Parc des Saphirs
Federal contribution
$586,675
Federal share33%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 6, 2021
2021202220232024
Built
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Municipality of Boischatel
- Construction start
- Jul 10, 2023(actual)
- Construction end
- Oct 7, 2024(actual)