Upgrading to standards the drinking water treatment plant

Boischatel, Quebec

completeDrinking WaterCWWF
Federal contribution
$4.6M
$4,620,451
Federal share50%

of $9.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2017
2017201820192020
Built

Approved 2 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Boischatel
Construction start
Sep 11, 2017(actual)
Construction end
Feb 17, 2020(actual)

Against the original forecast

  • Construction start4 months lateforecast May 15, 2017
  • Construction end4 months lateforecast Oct 31, 2019