Hudson's Bay Company Heritage Trail Completion
Federal contribution
$25,850
Federal share35%
of $73.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 13 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Hope Mountain Centre for Outdoor Learning
- Construction start
- Jun 1, 2015(actual)
- Construction end
- Dec 23, 2015(actual)
Also in Hope