Back to projects

Golden Snowmobile Trail Enhancements

Golden, British Columbia

completeRecreationNRT
Federal contribution
$17,000
Federal share50%

of $34.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2016
20152016
Built

Approved 17 months before the announcement.

Program
National Recreational Trails Program
Construction start
Nov 12, 2014(actual)
Construction end
Dec 28, 2015(actual)

Also in Golden

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50549 in the federal list. How to read these figures.