Golden Snowmobile Trail Enhancements
Federal contribution
$17,000
Federal share50%
of $34.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
20152016
Built
Approved 17 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Golden Snowmobile Trail Society and Club
- Construction start
- Nov 12, 2014(actual)
- Construction end
- Dec 28, 2015(actual)
Also in Golden
- Kicking Horse Canyon Project Phase 4: West Portal to Yoho Bridge$215.2M
- Kicking Horse Canyon Highway Improvement Project - Phase 2$62.5M
- Trans-Canada Highway 1 - Quartz Creek$49.9M
- Highway 1 Selkirk Mountain Four-Laning$31.5M
- TOWN OF GOLDEN: FLOOD RESILIENCE HIGHWAY 95, KICKING HORSE I & II BRIDGE$28.8M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50549 in the federal list. How to read these figures.