Trans-Québec Trail 55 - Ayer’s Cliff

Magog, Quebec

completeRecreationNRT
Federal contribution
$7,485
Federal share50%

of $15.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 30, 2009
2010
Built

Approved 2 months before the announcement.

Program
National Recreational Trails Program
Construction start
May 26, 2009(actual)
Construction end
Mar 31, 2010(actual)