Creston Valley Powersports Coalition-Maryland Boundary
Federal contribution
$19,140
Federal share50%
of $38.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
20152016
Built
Approved 14 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Kokanee Country Snowmobile Club
- Construction start
- Jan 15, 2015(actual)
- Construction end
- Nov 24, 2015(actual)
Also in Creston
- Arrow Creek Water Main Replacement and System Improvements - Final Phase$2.5M
- Creston - Wastewater Treatment Plant Improvements$1.6M
- Creston and District Facility Enhancement$1.0M
- Creston Wastewater Treatment Plant Improvements - Cover, Secondary Clarifier and Backup Power$833.3K
- Schikurski Pump Station Upgrade$371.7K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50575 in the federal list. How to read these figures.