Mont Arthabaska Park
Federal contribution
$13,000
Federal share35%
of $37.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 30, 2009
2010
Built
Approved 2 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Corporation du Colisée des Bois-Francs
- Construction start
- May 26, 2009(actual)
- Construction end
- Mar 31, 2010(actual)
Also in Victoriaville
- Protection and securing of the drinking water supply in the Beaudet Reservoir of the City of Victoriaville.$16.0M
- Victoriaville Performing Arts Centre$8.0M
- Upgrade of equipment of treatment of wastewater in the STEP$2.4M
- Replacement of ventilation systems serving the medical imaging sector (radiology and nuclear medicine)$1.4M
- Upgrade of the Arthabaska community center$1.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50611 in the federal list. How to read these figures.