ETN- Peter's River Bridge
Grand Falls-Windsor, Newfoundland and Labrador
Federal contribution
$40,000
Federal share50%
of $80.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
20152016
Built
Approved 17 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Newfoundland and Labrador Snowmobile Federation
- Construction start
- Nov 1, 2014(actual)
- Construction end
- Nov 20, 2015(actual)