Back to projects

ETN-Water Treatment Plant Road Washout Bridge Install

Grand Falls-Windsor, Newfoundland and Labrador

completeRecreationNRT
Federal contribution
$15,000
Federal share50%

of $30.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2016
20152016
Built

Approved 17 months before the announcement.

Program
National Recreational Trails Program
Construction start
Nov 1, 2014(actual)
Construction end
Nov 20, 2015(actual)

Also in Grand Falls-Windsor