District of Lunenburg Trails
Federal contribution
$31,370
Federal share30%
of $104.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 13 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Municipal District of Lunenburg
- Construction start
- Apr 1, 2015(actual)
- Construction end
- Dec 17, 2015(actual)