Ducks Unlimited Trail System Upgrade
Federal contribution
$33,500
Federal share23%
of $143.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 30, 2009
2010
Built
Approved 2 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Kentville Parks and Recreation Department
- Construction start
- May 26, 2009(actual)
- Construction end
- Mar 31, 2010(actual)
Also in Kentville
- Town of Kentville - Donald E. Hiltz Connector Road - Water, Storm & Sanitary Infrastructure$3.9M
- Town of Kentville Complete Active Transportation Network$1.5M
- Chester Avenue Water and Sewer Replacement$988.2K
- Regional Sewage Treatment Plant Upgrade$907.9K
- Kings County Active Transportation - Sidewalk Extensions/Additions$555.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50740 in the federal list. How to read these figures.