Waterfront Trail Improvements at Happy Ralph's
Federal contribution
$25,000
Federal share29%
of $84.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 8 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- City of St. Catharines
- Construction start
- Nov 2, 2015(actual)
- Construction end
- Dec 21, 2015(actual)
Also in St. Catharines
- St. Catharines Arts Centre$18.0M
- Carlisle Street Garage Replacement$9.3M
- HVAC; Handwashing and Washrooms; Online Learning Support; New Portable; Building Ventilation Controls; Creating New Classroom Space$7.8M
- Facility Expansion$3.9M
- Purchase three 60' buses and nine 40' buses to replace existing vehicles for conventional service$3.6M