Back to projects

Bridge Construction Driftwood River and Sheriff Creek

Cochrane, Ontario

completeRecreationNRT
Federal contribution
$346,368
Federal share50%

of $692.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2016
20152016
Built

Approved 16 months before the announcement.

Program
National Recreational Trails Program
Construction start
Nov 24, 2014(actual)
Construction end
Oct 28, 2015(actual)

Also in Cochrane

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50901 in the federal list. How to read these figures.