Back to projects

Sault Ste. Marie Hub Trail System

Sault Ste. Marie, Ontario

completeActive TransportationNRT
Federal contribution
$83,764
Federal share49%

of $172.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 30, 2009
2010
Built

Approved 2 months before the announcement.

Program
National Recreational Trails Program
Ultimate recipient
City of Sault Ste. Marie
Construction start
May 26, 2009(actual)
Construction end
Mar 31, 2010(actual)

Also in Sault Ste. Marie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51009 in the federal list. How to read these figures.