Water Membrane Replacement

Poplar Hill First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$40,207
Federal share31%

of $131.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
201820192020
Built

Approved 4 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Poplar Hill First Nation
Construction start
Jul 1, 2018(actual)
Construction end
Dec 31, 2019(actual)

Against the original forecast

  • Construction start16 months lateforecast Mar 1, 2017
  • Construction end3 months earlyforecast Mar 31, 2020

Also in Poplar Hill First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51161 in the federal list. How to read these figures.