Wastewater Lift Pump Replacement

Poplar Hill First Nation, Ontario

completeWastewaterCWWF
Federal contribution
$7,874
Federal share39%

of $20.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
201820192020
Built

Approved 4 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Poplar Hill First Nation
Construction start
Feb 12, 2019(actual)
Construction end
Sep 24, 2020(actual)

Against the original forecast

  • Construction start23 months lateforecast Mar 1, 2017
  • Construction end6 months lateforecast Mar 31, 2020

Also in Poplar Hill First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51162 in the federal list. How to read these figures.