Back to projects

Purchase and installation of on-board equipment – Fleet increase for installation of surveillance cameras phase

Laval, Quebec

completePublic TransitPTIF
Federal contribution
$88,049
Federal share50%

of $176.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 2, 2018
201820192020
Built

Approved 6 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Apr 11, 2017(actual)
Construction end
Dec 31, 2019(actual)