Sewage Lift Station - Safety Landing Rehabilitation
Chippewas of the Thames First Nation, Ontario
Federal contribution
$1,500
Federal share50%
of $3.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
20182019
Built
Approved 4 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Chippewas of the Thames First Nation
- Construction start
- Jan 31, 2019(actual)
- Construction end
- Mar 31, 2019(actual)
Against the original forecast
- Construction start2.1 years lateforecast Jan 3, 2017
- Construction end23 months lateforecast Apr 30, 2017
Also in Chippewas of the Thames First Nation
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51177 in the federal list. How to read these figures.