Design and Install Sequential Batch Reactor to ensure Safe Operations of Station

Chippewas of the Thames First Nation, Ontario

completeWastewaterCWWF
Federal contribution
$25,000
Federal share50%

of $50.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
2018
Built

Approved 4 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
May 1, 2018(actual)
Construction end
Jun 30, 2018(actual)

Against the original forecast

  • Construction start16 months lateforecast Jan 3, 2017
  • Construction end14 months lateforecast Apr 30, 2017

Also in Chippewas of the Thames First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51178 in the federal list. How to read these figures.