Back to projects

Bus shelter replacement in 2017

Laval, Quebec

completePublic TransitPTIF
Federal contribution
$112,502
Federal share50%

of $225.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2017
Built

Approved 2 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Mar 14, 2017(actual)
Construction end
Nov 14, 2017(actual)

Also in Laval

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51211 in the federal list. How to read these figures.