Back to projects

Replacement of service vehicles in 2018

Laval, Quebec

completePublic TransitPTIF
Federal contribution
$40,000
Federal share50%

of $80.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2017
2018
Built

Approved 2 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jul 1, 2018(actual)
Construction end
Jul 30, 2018(actual)

Also in Laval

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51218 in the federal list. How to read these figures.