Back to projects

Work to refurbish the garage at 2205 Francis-Hughes

Laval, Quebec

completePublic TransitPTIF
Federal contribution
$1.4M
$1,433,499
Federal share50%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2017
20182019
Built

Approved 2 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Aug 28, 2017(actual)
Construction end
Jul 16, 2019(actual)

Also in Laval